place in Brittany, France.
July 2006
Work continues on the master bedroom/en-suite and our new kitchen
August 2006
The kitchen roofs nearly on and the fittings start to go in the en-suit.
September 2006
The kitchen roof goes on and the windows and doors go in to make the shell watertight.
November 2006
The plastering is finished, the mezzanine is finished and the tiles start to be laid and the Aga arrives
December 2006
The floor tiling is finished and Graham makes a start on fitting all the guttering.
October 2006
The inside of the kitchen is started.